How the concrete calculator works
Choose a pour shape and enter its dimensions. The calculator finds its volume, multiplies identical footings, columns or post holes by How many, then adds a waste allowance. The main result includes waste and displays two decimal places; supporting rows separate the measured volume from the extra allowance.
Unit menus are linked: choosing a metric or imperial unit switches the other measurements and the bag-size choices. Results can show yd³, ft³ or m³. Choose a bag size, then open the optional waste, landing or cost settings when needed.
Concrete volume formulas
Use consistent length units before multiplying. For example, divide inches by 12 to get feet; divide cubic feet by 27 to get cubic yards.
| Shape | Volume formula |
|---|---|
| Slab | Length × width × thickness |
| Footing | Length × width × depth |
| Wall | Length × height × thickness |
| Column | π × (diameter ÷ 2)² × height |
| Round slab | π × (diameter ÷ 2)² × thickness |
| Post hole | max(0, hole area − post area) × max(0, depth − gravel) |
| Stairs | Width × rise × [run × n × (n − 1) ÷ 2 + top depth × n] |
| Curb and gutter | Length × (curb width × curb height + gutter width × gutter thickness) |
Count applies only to footings, columns and post holes. Other shapes use one piece. Calculations retain unrounded quantities.
Post holes are circular. The calculator subtracts a 3.5 in square for a 4×4 post, a 5.5 in square for a 6×6, or a circle with a fixed 2.375 in diameter for Round pipe. None subtracts no post area. Gravel reduces the concrete depth and must be shallower than the hole; max(0, …) prevents negative quantities.
Stairs are solid stepped blocks, not thin stair slabs over fill. Count the rises up to the top. With Add a landing at the top enabled, Landing depth replaces the top step's run at full stair height; it is not an extension added beyond that run.
For curb and gutter, curb height runs from bottom to top, and gutter width extends in front of the curb. Set gutter width to zero for a curb alone. Otherwise, gutter thickness must be less than curb height.
Worked example: a 10 × 10 ft slab
The default slab is 10 ft long, 10 ft wide and 4 in thick. Change the extra for waste is off, which leaves the default 10% allowance in place. The selected bag is 80 lb, and Estimate the cost is off.
- Volume before waste: 10 × 10 × (4 ÷ 12) = 33.3 ft³, or 1.23 yd³.
- Extra for waste: 3.3 ft³, bringing the total to 36.7 ft³.
- Concrete needed: the unrounded total ÷ 27 = 1.36 yd³.
- Bags: the unrounded total ÷ 0.60 = 61.11, rounded up to 62.
The purchase note reads: Order 1.5 yd³ of ready-mix or buy 62 × 80 lb bags. The ready-mix row shows 1 truck. The bags weigh 4,960 lb to carry, and the poured-weight estimate is 5,130 lb (2.6 tons). No cost rows have values because cost estimation is off.
Bag yields and whole-bag quantities
Bag count equals waste-adjusted volume divided by yield, rounded up. The U.S. yields match the QUIKRETE Concrete Mix data sheet. The comparison table shows all three sizes without changing the volume.
| Bag size | Yield per bag | Bags | Dry weight |
|---|---|---|---|
| 40 lb | 0.30 ft³ | 123 | 4,920 lb |
| 60 lb | 0.45 ft³ | 82 | 4,920 lb |
| 80 lbDefault | 0.60 ft³ | 62 | 4,960 lb |
Metric choices are 20, 25 and 30 kg, with estimated yields of 9.4, 11.7 and 14.1 L. These extrapolate the U.S. yield per unit mass; they are not specifications for every metric product. Yield cannot be edited, so check your bag's label before buying.
Ready-mix orders and poured weight
Below 1 yd³ in imperial mode, the purchase note emphasizes bags. From 1 through 3 yd³, it shows both options; above 3 yd³, it emphasizes ready-mix. Metric thresholds are 0.75 and 2.25 m³. These are display rules, not supplier minimums or a cost comparison.
Ready-mix quantity rounds up to a multiple of 0.25 yd³ or 0.25 m³. Truck count uses the waste-adjusted volume before that rounding, assuming 10 yd³ per truck, about 7.65 m³. Confirm capacity, order increments, minimum loads and fees with your supplier.
Poured weight uses approximately 140 lb/ft³, or 2,243 kg/m³, and rounds to the nearest 10 lb or kg. It includes waste but excludes additional material caused by bag or ready-mix purchase rounding. Imperial tons mean U.S. short tons of 2,000 lb; metric t means 1,000 kg.
Waste allowance and optional costs
NRMCA recommends ordering 4%–10% above plan volume for contingencies. This calculator uses 10% while Change the extra for waste is off. Switch it on to enter 0%–50%. Turning it off restores 10%; it does not remove waste.
Enable Estimate the cost to enter either or both prices. Bag cost is whole bags × price per bag. Ready-mix cost is rounded order quantity × price per yd³ or m³, plus Delivery and fees. A blank price hides that option's cost; blank fees count as zero. Update prices after changing bag size or units. Labor, forms, reinforcement and taxes are not added automatically.
Check measurements before ordering
- 1Measure the actual space. Use inside form dimensions and the prepared base level. For columns, enter the tube's inside diameter.
- 2Separate different sizes. How many repeats one identical footing, column or hole. Calculate differently sized pieces separately.
- 3Plan material handling. Check vehicle payload and delivery access. Dry-bag weight and poured weight describe different loads.
Frequently asked questions
How many bags of concrete make a cubic yard?
At the calculator's yields, one cubic yard requires 45 bags of 80 lb, 60 bags of 60 lb or 90 bags of 40 lb. Those counts exclude any waste allowance.
How many bags do I need per fence post?
The default 10 in diameter, 36 in deep hole, with 6 in of gravel and a 4×4 post, needs about 1.27 ft³ including waste. That is 2.1 bags of 80 lb, rounded to 3 for one hole; 10 identical holes need 22 bags because rounding happens after combining their volumes.
Why is the main volume smaller than the ready-mix order?
The main result is calculated volume plus waste, displayed to two decimals. The ready-mix order rounds that quantity upward to a quarter-unit multiple, so use the order row when discussing delivery quantities.
Does the calculator subtract openings or reinforcing steel?
No automatic deductions are made for wall openings, reinforcing steel or other embedded objects, apart from the selected post in Post hole mode. Post holes also assume concrete fills the depth above the gravel, without a separate soil-backfill allowance.
Sources
- 1QUIKRETE Concrete Mix, Product No. 1101: Technical data sheet · The QUIKRETE Companies · Accessed November 2026
- 2CIP 31: Ordering Ready Mixed Concrete · National Ready Mixed Concrete Association · Accessed November 2026
- 3NIST Guide to the SI, Appendix B.8: Factors for Units Listed Alphabetically · National Institute of Standards and Technology · Accessed November 2026
- 4Worker Safety Series: Concrete Manufacturing · Occupational Safety and Health Administration · Accessed November 2026
This is a quantity estimate; have a qualified professional confirm structural dimensions and local requirements.